Work Completed This Week
GBI started with grading for curb and gutter on the east side of San Pablo Avenue. They also started work on drainage systems.
RE Maher will complete reinforcing steel and placing concrete for retaining Wall B. They started work on curb, gutter, and sidewalk on the west side of San Pablo Avenue from Rivers Street moving north towards Robert Miller Drive.
MBE started work on the installation of foundations for the street lighting.
AVAR started drilling for production nails on the second row for the soil nail wall.
Work Forecast for Next Week
GBI will continue with grading for curb, gutter, and sidewalk on the west side of San Pablo Avenue. They will also continue with drainage systems.
RE Maher will continue with retaining wall B with reinforcing steel and placing concrete. They will start work on the curb, gutter, and sidewalk on the west side of San Pablo Avenue.
MBE will continue with work on the installation of the electrical system for lights and signals.
AVAR will start the installation of the next row of production nails.
For additional project information, visit the City’s website page at http://www.ci.san-pablo.ca.us or contact the City’s Construction Manager, Jaemin Park at (925) 818-3756 or by e-mail: jpark@park-eng.com.
English Weekly Newsletter 18