Work Completed This Week
GBI is working on drainage systems. They are also excavating retaining wall A and grading for curb, gutter, and sidewalk on the east side of San Pablo Avenue
RE Maher is continuing with curb, gutter, and sidewalk on the west side of San Pablo Avenue.
AVAR has completed productions nails on the second row for the soil nail wall. They have also shotcrete the second lift.
Work Forecast for Next Week
GBI will continue with drainage systems and grading for curb and gutter on the east side of San Pablo Avenue.
RE Maher will continue with curb, gutter, and sidewalk on the west side of San Pablo Avenue.
AVAR will start production nails on the third row.
For additional project information, visit the City’s website page at http://www.ci.san-pablo.ca.us or contact the City’s Construction Manager, Jaemin Park at (925) 818-3756 or by e-mail: jpark@park-eng.com.
English Weekly Newsletter 19