Work Completed This Week

GBI continued with drainage systems and grading for curb and gutter on the east side of San Pablo Avenue.  

RE Maher continued with curb, gutter, and sidewalk on the west side of San Pablo Avenue. 

AVAR continued with production soil nails on the third row.

Work Forecast for Next Week

GBI will continue with drainage systems and soil removal and grading.  They will also grade for curb and gutter on the east side of San Pablo Avenue and finish excavation for retaining wall A. 

RE Maher will continue with curb, gutter, and sidewalk on the west side of San Pablo Avenue.  Once complete, they will move over to the east side and start work on the curb and gutter.

 AVAR shotcrete the final lift of the soil nail wall.