Work Completed This Week
GBI continued work on roadway section north of Robert Miller and completing drainage systems.
RE Maher continued work on retaining wall A.
Work Forecast for Next Week
GBI will continue with roadway section north of Robert Miller and completing drainage systems.
RE Maher will complete retaining wall A.
MBE will be on site to continue with street lighting work.
For additional project information, visit the City’s website page at http://www.ci.san-pablo.ca.us or contact the City’s Construction Manager, Jaemin Park at (925) 818-3756 or by e-mail: jpark@park-eng.com.