News Flash

Public Works - Engineering

Posted on: October 1, 2018

[ARCHIVED] San Pablo Avenue Complete Streets Project - Weekly Updates(10/01/18)

Work Completed This Week

GBI continued work on roadway section north of Robert Miller and continued with drainage systems. 

RE Maher continued work on retaining wall A.

MBE is back on site working of street lighting north of Robert Miller.

Work Forecast for Next Week

GBI will continue with roadway section north of Robert Miller and completing drainage systems. 

RE Maher will complete retaining wall A and start working on curb gutter and sidewalk on the east side of San Pablo from Rivers to Lancaster.

MBE will be on site to continue with street lighting work.


For additional project information, visit the City’s website page at http://www.ci.san-pablo.ca.us or contact the City’s Construction Manager, Jaemin Park at (925) 818-3756 or by e-mail: jpark@park-eng.com.