Work Completed This Week
GBI continued work on roadway section north of Robert Miller and continued with drainage systems.
RE Maher working on the J-Ditch above the soil nail wall. They are also working on median curb north of Robert Miller Drive.
Work Forecast for Next Week
GBI will continue with roadway section north of Robert Miller and completing drainage systems.
RE Maher will continue with median curb north of Robert Miller Drive.
For additional project information, visit the City’s website page at http://www.ci.san-pablo.ca.us or contact the City’s Construction Manager, Jaemin Park at (925) 818-3756 or by e-mail: jpark@park-eng.com.