Work Completed This Week
GBI switched traffic on San Pablo Avenue from Robert Miller Drive north, shifting traffic to the outside lanes and closing the inside lanes adjacent to the median.
GBI paved sections of the median area and continued with construction of the roadway section in the inside lanes north of Robert Miller Drive.
RE Maher continued with median curb north of Robert Miller Drive.
Work Forecast for Next Week
GBI will continue with construction of median area and continue with construction of the roadway section in the inside lanes north of Robert Miller Drive.
RE Maher will continue with median curb north of Robert Miller Drive. They will also work on curb gutter and sidewalk on the east side of San Pablo Avenue from Rivers Street to Lancaster.
For additional project information, visit the City’s website page at http://www.ci.san-pablo.ca.us or contact the City’s Construction Manager, Jaemin Park at (925) 818-3756 or by e-mail: jpark@park-eng.com.