Work Completed This Week
GBI continued with construction of median area and continued with construction of the roadway section in the inside lanes north of Robert Miller Drive.
RE Maher continued with median curb north of Robert Miller Drive. They also worked on curb gutter and sidewalk on the east side of San Pablo Avenue from Rivers Street to Lancaster.
Work Forecast for Next Week
GBI will continue with construction of median area and continue with construction of the roadway section in the inside lanes north of Robert Miller Drive.
RE Maher will continue with median curb north of Robert Miller Drive. They will also work on curb gutter and sidewalk on the east side of San Pablo Avenue from Rivers Street to Lancaster.
AVAR will be in to start work on the rock facing for the soil nail wall.
For additional project information, visit the City’s website page at http://www.ci.san-pablo.ca.us or contact the City’s Construction Manager, Jaemin Park at (925) 818-3756 or by e-mail: jpark@park-eng.com.