News Flash Home
The original item was published from 1/7/2019 6:05:20 PM to 3/11/2019 12:00:03 AM.

News Flash

Public Works - Engineering

Posted on: December 10, 2018

[ARCHIVED] San Pablo Avenue Complete Streets Project - Weekly Updates(12/10/18)

Work Completed This Week

GBI continued to support RE Maher for completing the curb, gutter, and sidewalk on the west side of San Pablo Avenue.  

RE Maher will continue with curb, gutter, and sidewalk on the west side of San Pablo Avenue, north of Robert Miller Drive.  They will also start working on the J-ditch above the soil nail wall.

Mike Brown Electric continued with street lighting installation.

Work Forecast for Next Week

GBI will continue to support RE Maher for completing the curb, gutter, and sidewalk on the west side of San Pablo Avenue and the J-ditch behind the soil nail wall.  

RE Maher will continue with curb, gutter, and sidewalk on the west side of San Pablo Avenue, north of Robert Miller Drive.  They will also continue working on the J-ditch above the soil nail wall.

Mike Brown Electric will work on street lighting and new signals.


For additional project information, visit the City’s website page at http://www.ci.san-pablo.ca.us or contact the City’s Construction Manager, Jaemin Park at (925) 818-3756 or by e-mail: jpark@park-eng.com.


English Weekly Newsletter 35

Facebook Twitter Email