Work Completed This Week
GBI continued to support RE Maher for completing the curb, gutter, and sidewalk on the west side of San Pablo Avenue.
RE Maher will continue with curb, gutter, and sidewalk on the west side of San Pablo Avenue, north of Robert Miller Drive. They will also start working on the J-ditch above the soil nail wall.
Mike Brown Electric continued with street lighting installation.
Work Forecast for Next Week
GBI will continue to support RE Maher for completing the curb, gutter, and sidewalk on the west side of San Pablo Avenue and the J-ditch behind the soil nail wall.
RE Maher will continue with curb, gutter, and sidewalk on the west side of San Pablo Avenue, north of Robert Miller Drive. They will also continue working on the J-ditch above the soil nail wall.
Mike Brown Electric will work on street lighting and new signals.
For additional project information, visit the City’s website page at http://www.ci.san-pablo.ca.us or contact the City’s Construction Manager, Jaemin Park at (925) 818-3756 or by e-mail: jpark@park-eng.com.