Work Completed This Week
GBI is working on cleaning up the site in preparation of grinding and paving. They are removing the concrete at the northeast corner of Rivers and San Pablo Avenue to reconstruct the sidewalk and curb ramp.
RE Maher completed work on median concrete throughout the project.
Mike Brown Electric worked on street lighting and new signals.
RMT is on site to install trees and decomposed granite in the median areas
Work Forecast for Next Week
GBI will continue with completing miscellaneous items in preparation of grinding and paving in the coming weeks.
Mike Brown electric will continue with signals and street lighting.
RMT will continue to work on planting trees and placing decomposed granite in the median areas.