Work Completed This Week
Due to the continued rain over that last few weeks, paving on San Pablo Avenue was delayed until last week. On March 13, 2019, the remaining paving of the inside lanes on northbound and southbound San Pablo Avenue was completed.
This week, the contractor completed raising iron and cat tracked the striping for the lane lines. They also completed some minor finish work, including concrete work and signage.
Work Forecast for Next Week
Contractor will be completing final striping and miscellaneous finish work to complete the project.
For additional project information, visit the City’s website page at http://www.ci.san-pablo.ca.us or contact the City’s Construction Manager, Jaemin Park at (925) 818-3756 or by e-mail: jpark@park-eng.com.