Work Completed This Week
Contractor has been working on finishing up remaining minor items of work. Ghilotti Brothers have been working on installing bollards at Rivers and at the bike path at Robert Miller Drive. They have also been working on repaving the driveway at the self-storage facility on the east side of San Pablo Avenue.
Bayside Striping completed all lane line striping on the project and the green bike lane striping from Rivers Street north on San Pablo Avenue.
Mike Brown Electric has installed final signals throughout the project
Work Forecast for Next Week
Contractor will be completing the green thermoplastic bike lane striping south of Rivers Street. They will also complete all remaining streetlights and signal hookups, once PG&E provides the necessary power at La Puerta.
Some needed minor punch list work for will be performed throughout the project.